Race Bank Onshore Sub-Station Walpole St Peter
Posted on
Anglia Formwork have started work at Race Bank Onshore Sub-station completing the FRC work’s for J.N. Murphy and their client DONG Energy. The substation will consist of a number of concrete structures such as water retaining bunds for transformers and shunt reactors, harmonic filters and numerous other equipment foundations.
We just started the foundations for the GIS Building which has around 50 tonne of reinforcement and 500m3 of concrete, we are currently waterproofing the structure using Grace Constructions Preprufe 300R & 800PA.