New Basement for South Pickenham Hall
Posted on
Anglia Formwork has just completed the RC works for the basement of the new extension to South Pickenham Hall. The build went along steadily but due to late design detail the job was delayed by two weeks. With a few modifications to our program we were able to successfully accelerate and regain the 2 weeks which allowed us to finish in time for the steel structure to be erected to get the job back on track.
Program Duration: 8 Weeks (reduced to 6)
Concrete: 625 m3
Reinforcement: 60 Tonne