Anglia Formwork Limited are pleased to have completed another package of works for Bam Farrans JV Great Yarmouth Third River Crossing scheme.
It saw us construct two RC curved retaining walls, one 7m and the other 21m in length on the eastern approach of the embankment to the new bridge.